Update
Residential building - 1/2 the building is 3 stories up with the roof sheathed.
We will be drying this half of the building in this week.
Commercial space roof trusses are starting to get set.
Monday, May 8, 2017
Progress Update
We are pumping the frost walls of the commercial space.
The next portion of the pre-cast is grouted and ready for concrete topping.
With 20 guys on site - 2nd floor framing is nearly complete with guys prepping the 3rd floor trusses.
Friday, April 28, 2017
Foundation Complete
The last portion of the foundation is poured and forms are being removed.
We will start setting the last of the pre-cast on Wednesday.
Wednesday, April 12, 2017
Update
Exterior and hall walls are starting to go up.
Concrete topping is being installed.
Foundation wall forms are being removed.
Monday, April 10, 2017
Ashpalt Crushing
We have started crushing the removed asphalt on site.
Also the framers have started today!
Thursday, March 30, 2017
Foundation / Pre-Cast Update
Wednesday, March 15, 2017
Foundation Upate