Friday, April 28, 2017

Foundation Complete

The last portion of the foundation is poured and forms are being removed. 
We will start setting the last of the pre-cast on Wednesday. 

Wednesday, April 12, 2017

Update

Exterior and hall walls are starting to go up.



Concrete topping is being installed.

Foundation wall forms are being removed.

Monday, April 10, 2017

Ashpalt Crushing

We have started crushing the removed asphalt on site.
Also the framers have started today!